Gantt charts

The start date for a fence construction project is 10 February. This incomplete Gantt chart shows a task list with start dates and estimated durations (ED) in days for each task. For each task, select the start date on the timescale in the appropriate row. Aim to overlap some tasks in order to shorten the overall project duration.

Gantt chart for brick fence construction project

Picture of a Gantt chart related to the brick fence construction project

If you have any questions about this Gantt chart, speak to your trainer.