Preceding events table

Task ID Task Days Preceding events
52 Lock up complete 0  
  Fixing and fittings    
53 Plaster walls 5 52
54 Internal joinery (cupboards, pantries, built-in robes etc) 4 53
55 Fix skirting boards, architraves 3 54
56 Fit internal doors 3 55
57 Plumbing fit-off 2 56
58 Electrical fit-off 3 54
59 Painting 10 56
60 Gas inspection 0.5 57
61 Electrical inspection 0.5 58
62 Sewerage inspection 0.5 57
63 Complete fittings and fixtures 0
59, 61, 62